Invitation to Tender
Detailed Design for Weir Mitigation Works for 2 Weirs
The Successful contractor is expected to, using the existing feasibility study and options appraisal;
•           Develop a preferred option for the mitigation measures for both weirs working with WWT and partners
•           Complete flow and flood modelling for the preferred options
•           Complete detailed design specification for the preferred options
•           Complete a full cost break down for construction of the preferred option
The final report will be presented to WWT and key stakeholders. The report will be prepared in plain English, with a clear explanation of the decisions reached.  The report should be prepared in a format that is usable by project staff and partners.
Timescales
We require tenders to be returned by Monday 15th February 2021 10am on Friday 19th February 2021.Â
The successful contractor will be appointed on Friday 19th February 2021.
The contract for the work will commence on Monday the 22nd February 2021.
We require the assessment to be completed by the Friday 30th April 2021